Scaffolding SWMS template
Erecting and dismantling scaffold involves a risk of falling more than 2 metres, so it is high risk construction work and needs a SWMS. This one covers planning, delivery, the base, erecting each lift, edge protection and ties, the handover inspection, and dismantling. Change it for your scaffold and download it.
Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.
The scaffolding SWMS
7 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.
- Work activity
- Erection, alteration and dismantling of modular scaffold to a two-storey building, more than 4 metres high, including handover to other trades.
- High risk construction work
-
- Risk of a fall of more than 2 metres
- PPE
- Hard hat, Safety glasses, Hi-vis clothing, Steel-cap boots, Work gloves, Fall-arrest harness, Sun protection (hat, long sleeves, SPF 50+)
- Plant and equipment
- Modular scaffold components
- Sole boards and base plates
- Gin wheel or materials hoist
- Harness and lanyard
- Scaffold tags and handover certificates
- Barricades and signs
- Licences and training
- General construction induction (White Card)
- Scaffolding licence (SB, SI or SA) for scaffold over 4 metres
- Working at heights training
| # | Job step | Hazards | Risk | Control measures | Residual | Responsible |
|---|---|---|---|---|---|---|
| 1 | Plan the scaffold and check the site |
| High |
| Medium | Supervisor |
| 2 | Unload and move components |
| Medium |
| Low | All workers |
| 3 | Set up the base |
| High |
| Low | Licensed scaffolder |
| 4 | Erect each lift |
| High |
| Medium | Licensed scaffolder |
| 5 | Install ties, access and containment |
| High |
| Low | Licensed scaffolder |
| 6 | Inspect and hand over |
| High |
| Low | Licensed scaffolder |
| 7 | Dismantle |
| High |
| Medium | Licensed scaffolder |
Rules that apply to scaffolding work
- A scaffolding high risk work licence (basic, intermediate or advanced) is needed to erect, alter or dismantle scaffold where a person or object could fall more than 4 metres.
- Scaffold over 4 metres is inspected by a competent person before first use, after alterations or repairs, after events like storms, and at least every 30 days.
- Follow the manufacturer's instructions and AS/NZS 4576 (guidelines for scaffolding) and AS/NZS 1576 (scaffolding standards).
- Install edge protection as each lift goes up rather than at the end.
Questions
Do you need a licence to put up scaffold?
How often does scaffold need to be inspected?
What should a scaffold handover include?
Is this scaffolding SWMS free to use?
More SWMS templates
- Working at heights
- Electrical
- Carpentry
- Plumbing
- Air conditioning
- Solar installation
- Roofing
- Concreting
- Excavation
- Demolition
- Painting
- Tiling
- Landscaping
- Builders clean
- Pest control
By state: SWMS template NSW · SWMS template QLD · SWMS template VIC · SWMS template WA · SWMS template SA · Blank SWMS template
Attach the SWMS to every job
Fieldmox runs quotes, scheduling, the technician app and invoicing in one place. Save the SWMS on the job next to the quote and photos, so it's there when the builder asks for it, and add "SWMS read and signed" to the visit checklist your crew ticks off on their phone before they start.
Book a meeting