Roofing SWMS template
Roof work almost always involves a risk of falling more than 2 metres, so it is high risk construction work and needs a SWMS. This one covers checking the roof, edge protection, access, lifting sheets, laying and fixing, cutting, and heat. Change it for your job and download it.
Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.
The roofing SWMS
7 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.
- Work activity
- Removing and replacing metal roof sheeting, gutters and flashings on a single- or two-storey building, including work at height of more than 2 metres.
- High risk construction work
-
- Risk of a fall of more than 2 metres
- PPE
- Safety glasses, Hearing protection, Hi-vis clothing, Steel-cap boots, Cut-resistant gloves, Fall-arrest harness, Sun protection (hat, long sleeves, SPF 50+)
- Plant and equipment
- Roof edge protection and scaffold
- Safety mesh
- Materials hoist or crane for sheets
- Nibbler, shears, drop saw, screw guns
- Harness, lanyard and certified anchors
- Tested and tagged tools with RCD
- Licences and training
- General construction induction (White Card)
- Roofing licence where the state requires one
- Working at heights training
- Dogging licence (DG) if slinging crane loads
| # | Job step | Hazards | Risk | Control measures | Residual | Responsible |
|---|---|---|---|---|---|---|
| 1 | Inspect the roof and plan the job |
| High |
| Medium | Supervisor |
| 2 | Install edge protection and access |
| High |
| Low | Supervisor |
| 3 | Lift roofing materials |
| High |
| Medium | All workers |
| 4 | Remove old sheeting and lay new sheets |
| High |
| Medium | All workers |
| 5 | Cut and fix sheeting and flashings |
| Medium |
| Low | All workers |
| 6 | Work in heat and sun |
| Medium |
| Low | Supervisor |
| 7 | Clean up and dismantle |
| Medium |
| Low | Supervisor |
Rules that apply to roofing work
- Treat every roof as fragile until proven otherwise: skylights, old fibre cement and rusted sheeting won't hold a person.
- Install roof edge protection (AS/NZS 4994) or scaffold before work starts. Use safety mesh (AS/NZS 4389) under new metal roofing.
- Asbestos cement roofs must not be walked on without crawl boards and fall protection, and must not be pressure washed or cut with power tools.
- Fall-arrest anchors must be installed and certified for the purpose (AS/NZS 5532).
Questions
Do roofers need a SWMS?
Can you walk on an asbestos cement roof?
Is safety mesh required under a new metal roof?
Is this roofing SWMS free to use?
More SWMS templates
- Working at heights
- Electrical
- Carpentry
- Plumbing
- Air conditioning
- Solar installation
- Scaffolding
- Concreting
- Excavation
- Demolition
- Painting
- Tiling
- Landscaping
- Builders clean
- Pest control
By state: SWMS template NSW · SWMS template QLD · SWMS template VIC · SWMS template WA · SWMS template SA · Blank SWMS template