Excavation SWMS template

Excavation needs a SWMS when it involves a trench or shaft deeper than 1.5 metres, a tunnel, or work where powered mobile plant is moving, which covers most excavator work. This one covers locating services, setting up, digging, supporting trenches, entering and backfilling. Edit it for your site and download it.

Edit it online

Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.

The excavation SWMS

7 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.

Work activity
Excavating trenches and footings with an excavator, including trenches deeper than 1.5 metres, and backfilling and compacting.
High risk construction work
  • Shaft or trench deeper than 1.5 m, or a tunnel
  • Where powered mobile plant is moving
PPE
Hard hat, Safety glasses, Hearing protection, Hi-vis clothing, Steel-cap boots, Work gloves, Sun protection (hat, long sleeves, SPF 50+)
Plant and equipment
  • Excavator with quick hitch and locking pin
  • Trench shields or shoring boxes
  • Vacuum truck or hand tools for potholing
  • Plate compactor
  • Gas detector for deep trenches
  • Barricades and trench covers
Licences and training
  • General construction induction (White Card)
  • Excavator operator competency (VOC or equivalent)
  • Traffic control training if working on a road
Job steps, hazards, risk ratings and control measures
# Job step Hazards Risk Control measures Residual Responsible
1 Locate underground services
  • Striking gas, electrical, water or telecommunications services
High
  • Get Before You Dig Australia plans and keep them on site
  • Locate and mark services; pothole by hand or vacuum to expose them
  • Keep machine digging away from exposed services as the asset owner requires
  • Every worker reads and signs this SWMS
Medium Supervisor
2 Set up the site
  • Excavator striking people
  • Members of the public
  • Overhead powerlines
High
  • Set up an exclusion zone around the excavator's swing radius
  • Fence or barricade the site from the public
  • Check the distance to powerlines; use a spotter if the machine works near the no-go zone
Low Supervisor
3 Operate the excavator
  • Rollover on slopes or soft ground
  • Bucket falling off the quick hitch
  • Workers in the blind spot
High
  • Do the pre-start check and record it
  • Insert and check the quick hitch locking pin every time an attachment is changed
  • Wear the seatbelt; keep the machine level and away from trench edges
  • Nobody approaches until the operator has seen them and lowered the bucket
Low Operator
4 Support trenches deeper than 1.5 metres
  • Trench wall collapse burying a worker
  • Spoil or materials falling in
High
  • Install shoring or trench shields, or bench or batter the walls, before entry
  • A competent person checks the support before each shift and after rain
  • Keep spoil, materials and machines at least 1 m back from the edge
Medium Supervisor
5 Enter and work in the trench
  • Falls into the trench
  • Low oxygen or toxic gases
  • Water inflow
High
  • Use a ladder within easy reach for getting in and out
  • Test the air in deep or enclosed trenches before entry
  • Pump out water; stop work if the walls get wet or move
  • Someone stays at the top while workers are in the trench
Medium All workers
6 Backfill and compact
  • Carbon monoxide from petrol compactors
  • Vibration and noise
  • Damaging services
Medium
  • Use electric or diesel compactors in trenches, or ventilate; never run petrol engines in a confined trench
  • Wear hearing protection and rotate operators
  • Backfill around services by hand with the specified bedding
Low All workers
7 Leave the site safe
  • People or animals falling into open excavations
High
  • Cover or fence open trenches at the end of every day
  • Lower the bucket to the ground and remove the key from the excavator
Low Supervisor

Rules that apply to excavation work

  • Get Before You Dig Australia plans before you dig, and expose services by hand or vacuum before using a machine near them.
  • Trenches deeper than 1.5 metres must be supported (shoring, benching or battering) before anyone enters.
  • Check the excavator's quick hitch locking pin is in before every lift and every dig.
  • Petrol compactors and pumps in trenches can build up carbon monoxide. Use them in the open or ventilate.

Questions

When does excavation need a SWMS?
When the work is in or near a shaft or trench deeper than 1.5 metres, or a tunnel, or where powered mobile plant such as an excavator is moving. Most machine excavation falls into at least one of these.
What is the 1.5 metre trench rule?
A trench with an excavated depth greater than 1.5 metres is high risk construction work. You need a SWMS, and the trench walls must be supported by shoring, benching or battering before anyone works in it.
How do I find underground services before digging?
Lodge a free request with Before You Dig Australia for plans, then have the services located and marked on site. Expose them by hand or vacuum excavation before digging near them with a machine.
Is this excavation SWMS free to use?
Yes. Download it as Word or PDF with no sign-up, or open it in the online builder to change the steps and add your business details first. Check it against your own job and site before you use it.