Demolition SWMS template
Demolishing a load-bearing or structural element is high risk construction work, and so is work likely to disturb asbestos, so demolition needs a SWMS before it starts. This one covers the hazardous materials survey, disconnecting services, site set-up, strip-out, structural and machine demolition, and waste. Edit it for your job and download it.
Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.
The demolition SWMS
7 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.
- Work activity
- Demolition of an internal load-bearing wall and strip-out of a residential building, including removal of building materials and waste.
- High risk construction work
-
- Risk of a fall of more than 2 metres
- Demolition of load-bearing or structural elements
- Disturbing asbestos
- Structural alterations needing temporary support
- Where powered mobile plant is moving
- PPE
- Hard hat, Safety glasses, Hearing protection, Hi-vis clothing, Steel-cap boots, Cut-resistant gloves, P2 respirator, Coveralls
- Plant and equipment
- Temporary props and acrow props
- Demolition saw, jackhammer, reciprocating saw
- Excavator or mini loader with demolition attachments (if used)
- Skip bins and chutes
- Water spray for dust
- Licences and training
- General construction induction (White Card)
- Demolition licence where the state requires one
- Licensed asbestos removalist for asbestos removal
- Plant operator competency
| # | Job step | Hazards | Risk | Control measures | Residual | Responsible |
|---|---|---|---|---|---|---|
| 1 | Survey for hazardous materials |
| High |
| Medium | Supervisor |
| 2 | Disconnect services |
| High |
| Low | Supervisor |
| 3 | Set up the site |
| High |
| Low | Supervisor |
| 4 | Strip out linings, fixtures and fittings |
| Medium |
| Low | All workers |
| 5 | Install temporary support and remove structural elements |
| High |
| Medium | Supervisor |
| 6 | Machine demolition and loading |
| High |
| Medium | Operator |
| 7 | Control dust and remove waste |
| Medium |
| Low | All workers |
Rules that apply to demolition work
- Asbestos identified before demolition must be removed first, by a licensed asbestos removalist where the law requires one.
- Get an engineer's demolition plan for structural elements, and install temporary support before removing anything load-bearing.
- Some states and councils require a demolition licence or permit for certain work. Check before you quote.
- Lead paint is common in homes built before 1970. Don't burn or dry-sand it.
Questions
When does demolition need a SWMS?
Do I need an asbestos survey before demolition?
Do I need a licence to do demolition?
Is this demolition SWMS free to use?
More SWMS templates
- Working at heights
- Electrical
- Carpentry
- Plumbing
- Air conditioning
- Solar installation
- Roofing
- Scaffolding
- Concreting
- Excavation
- Painting
- Tiling
- Landscaping
- Builders clean
- Pest control
By state: SWMS template NSW · SWMS template QLD · SWMS template VIC · SWMS template WA · SWMS template SA · Blank SWMS template
Attach the SWMS to every job
Fieldmox runs quotes, scheduling, the technician app and invoicing in one place. Save the SWMS on the job next to the quote and photos, so it's there when the builder asks for it, and add "SWMS read and signed" to the visit checklist your crew ticks off on their phone before they start.
Book a meeting