Concreting SWMS template

Concreting usually needs a SWMS because concrete trucks, pumps and other powered mobile plant move around the work area, which is high risk construction work. This one covers truck access, formwork and reo, the pump, placing and finishing, saw cutting and wash-out. Change the steps to suit the pour and download it.

Edit it online

Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.

The concreting SWMS

6 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.

Work activity
Placing and finishing a concrete slab or driveway: formwork, reinforcement, pumping or chute placement, finishing, saw cutting and clean-up.
High risk construction work
  • Where powered mobile plant is moving
PPE
Safety glasses, Hearing protection, Hi-vis clothing, Steel-cap boots, Chemical-resistant gloves, P2 respirator, Sun protection (hat, long sleeves, SPF 50+), Knee pads
Plant and equipment
  • Concrete agitator truck
  • Concrete boom or line pump
  • Vibrator, screeds, bull float, power trowel
  • Concrete saw (wet cut) with extraction
  • Gumboots, wash-out bin
Licences and training
  • General construction induction (White Card)
  • Concrete boom pump licence (CP) for the pump operator
  • Traffic control training if directing trucks on a road
Job steps, hazards, risk ratings and control measures
# Job step Hazards Risk Control measures Residual Responsible
1 Set up access for trucks and the pump
  • Reversing trucks striking workers
  • Truck or pump on soft ground
  • Overhead powerlines
  • Public and traffic
High
  • Plan the truck route and use a spotter for all reversing
  • Set the pump outriggers on firm ground with pads
  • Check the distance to powerlines; keep the boom outside the no-go zone
  • Set up traffic control if trucks stand on the road
  • Every worker reads and signs this SWMS
Medium Supervisor / pump operator
2 Build formwork and lay reinforcement
  • Back strain
  • Impalement on starter bars and pegs
  • Cuts from mesh and wire
Medium
  • Cap starter bars and form pegs
  • Team lift mesh sheets; wear cut-resistant gloves
  • Keep walkways clear of off-cuts
Low All workers
3 Pump and place the concrete
  • Hose whip and line blockages
  • Boom failure or contact
  • Slips on wet concrete
High
  • Only the pump operator and hose hand near the delivery hose; keep the rest clear
  • Never put hands near the hopper or the end of a blocked line under pressure
  • Check the pump's daily inspection is done
  • Wear gumboots and move steadily on wet surfaces
Medium Pump operator
4 Spread, screed and finish
  • Cement burns to skin and eyes
  • Manual handling and repetitive strain
  • Heat and UV
Medium
  • Wear waterproof gloves, gumboots, long sleeves and glasses
  • Wash concrete off skin straight away; keep eyewash on site
  • Rotate tasks; use long-handled tools
  • Pour early on hot days; provide shade and water
Low All workers
5 Saw cut joints and grind
  • Crystalline silica dust
  • Noise
  • Blade kickback or shattering
  • Petrol saw exhaust
High
  • Wet cut or use on-tool extraction; never dry cut without extraction
  • Wear a P2 respirator, hearing protection and a face shield
  • Check blades are rated for the saw speed and fitted correctly
  • Don't run petrol saws in enclosed areas
Low All workers
6 Wash out and clean up
  • Concrete slurry entering stormwater
  • Cement burns
Medium
  • Use a wash-out bin or bunded area, never the gutter or drain
  • Wear gloves and glasses during wash-out
Low Supervisor

Rules that apply to concreting work

  • Wet concrete is strongly alkaline and causes chemical burns. Keep it off skin and out of eyes.
  • Cutting, grinding and drilling cured concrete releases crystalline silica dust. Use wet cutting or on-tool extraction and wear a P2 respirator.
  • Operating a concrete boom pump needs a CP high risk work licence.
  • Keep pump booms and trucks outside the no-go zone for overhead powerlines.

Questions

Do concreters need a SWMS?
Most do. Concrete trucks, pumps, bobcats and excavators are powered mobile plant, and working where they move is high risk construction work. Pours on or next to a road in use, tilt-up and precast work, and suspended slabs with fall risk are also high risk construction work.
How do I control silica dust when cutting concrete?
Cut wet or with on-tool dust extraction, wear a P2 (or better) respirator, and keep other people away while you cut. Don't dry-sweep the dust afterwards; vacuum it with an H-class vacuum or wet it down.
Why are cement burns so serious?
Wet concrete is strongly alkaline. It can burn skin without much pain at first, especially when it soaks through clothes or into boots. Wash it off straight away and wear waterproof gloves and gumboots.
Is this concreting SWMS free to use?
Yes. Download it as Word or PDF with no sign-up, or open it in the online builder to change the steps and add your business details first. Check it against your own job and site before you use it.