Free template · Australia · Updated November 2026
Painting SWMS template
Painters need a SWMS when the job has a risk of falling more than 2 metres, such as a two-storey exterior, or other high risk construction work. This one covers set-up, pressure washing, surface prep and lead paint, access at height, brush, roller and spray application, and clean-up. Edit it for your job and download it.
Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.
The painting SWMS
7 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.
- Work activity
- Exterior and interior repaint of a two-storey house: pressure washing, surface preparation, and brush, roller and spray application, including work at height of more than 2 metres.
- High risk construction work
-
- Risk of a fall of more than 2 metres
- PPE
- Safety glasses, Steel-cap boots, Chemical-resistant gloves, P2 respirator, Fall-arrest harness, Sun protection (hat, long sleeves, SPF 50+), Coveralls
- Plant and equipment
- Mobile scaffold or EWP for upper storey
- Platform and extension ladders (industrial rated)
- Pressure washer
- Airless spray unit
- Sanders with dust extraction, HEPA vacuum
- Drop sheets and paint storage
- Licences and training
- General construction induction (White Card)
- Painting licence or registration where the state requires it
- EWP training for the unit used
- Lead-safe work training (recommended for pre-1970 homes)
| # | Job step | Hazards | Risk | Control measures | Residual | Responsible |
|---|---|---|---|---|---|---|
| 1 | Set up and protect the work area |
| Low |
| Low | Supervisor |
| 2 | Pressure wash surfaces |
| Medium |
| Low | All workers |
| 3 | Prepare surfaces and deal with old paint |
| High |
| Medium | Supervisor |
| 4 | Access upper walls, eaves and gutters |
| High |
| Medium | All workers |
| 5 | Apply paint by brush and roller |
| Medium |
| Low | All workers |
| 6 | Spray painting |
| High |
| Medium | Sprayer |
| 7 | Clean up and store products |
| Medium |
| Low | All workers |
Rules that apply to painting work
- Homes built before 1970 often have lead paint. Test before sanding, use wet methods, and never burn it off.
- Spray painting with solvent-based products needs ventilation and a respirator with the right cartridge for organic vapours.
- Read the safety data sheet (SDS) for each product and keep it on site.
- Don't wash brushes or tip paint into stormwater drains.
Questions
Do painters need a SWMS?
How do I know if old paint contains lead?
What respirator do I need for spray painting?
Is this painting SWMS free to use?
More SWMS templates
- Working at heights
- Electrical
- Carpentry
- Plumbing
- Air conditioning
- Solar installation
- Roofing
- Scaffolding
- Concreting
- Excavation
- Demolition
- Tiling
- Landscaping
- Builders clean
- Pest control
By state: SWMS template NSW · SWMS template QLD · SWMS template VIC · SWMS template WA · SWMS template SA · Blank SWMS template
Attach the SWMS to every job
Fieldmox runs quotes, scheduling, the technician app and invoicing in one place. Save the SWMS on the job next to the quote and photos, so it's there when the builder asks for it, and add "SWMS read and signed" to the visit checklist your crew ticks off on their phone before they start.
Book a meeting