Plumbing SWMS template
Plumbers need a SWMS when the job includes high risk construction work, such as a trench deeper than 1.5 metres, work on pressurised gas piping, or an area that may have a contaminated atmosphere like a sewer. This one covers finding services, trenching, sewer work, gasfitting, hot work and testing. Edit it for your job and download it.
Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.
The plumbing SWMS
7 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.
- Work activity
- Plumbing, drainage and gasfitting on a residential or commercial site, including excavating for drainage, connecting to existing sewer, and work on existing gas piping.
- High risk construction work
-
- Shaft or trench deeper than 1.5 m, or a tunnel
- On or near pressurised gas mains or piping
- Contaminated or flammable atmosphere
- PPE
- Safety glasses, Hearing protection, Hi-vis clothing, Steel-cap boots, Work gloves, Chemical-resistant gloves, P2 respirator, Sun protection (hat, long sleeves, SPF 50+)
- Plant and equipment
- Mini excavator (if used) and shoring boxes
- Pipe cutters, drop saw, press tools
- Oxy-acetylene or air-acetylene kit, fire extinguisher
- Gas detector
- Pressure test gauge
- Tested and tagged tools with RCD
- Licences and training
- General construction induction (White Card)
- Plumbing licence and gasfitting licence for the state
- Confined space entry training (only if entering pits)
- Hepatitis A and tetanus vaccinations recommended for sewer work
| # | Job step | Hazards | Risk | Control measures | Residual | Responsible |
|---|---|---|---|---|---|---|
| 1 | Locate services and set up |
| High |
| Low | Supervisor |
| 2 | Excavate trenches for drainage |
| High |
| Medium | Supervisor / operator |
| 3 | Work on existing sewer and stormwater |
| High |
| Medium | Licensed plumber |
| 4 | Cut and join pipe |
| High |
| Low | All workers |
| 5 | Gasfitting on existing gas piping |
| High |
| Low | Licensed gasfitter |
| 6 | Brazing and soldering (hot work) |
| High |
| Low | Licensed plumber |
| 7 | Test, commission and backfill |
| Medium |
| Low | Licensed plumber |
Rules that apply to plumbing work
- Get Before You Dig Australia plans before excavating, and expose services by hand or vacuum before using machines near them.
- Trenches deeper than 1.5 metres need shoring, benching or battering before anyone goes in.
- Never enter a sewer pit or tank unless it has been assessed as safe or you hold a confined space permit and training.
- Asbestos cement pipe is common in older drainage: don't cut it with power tools.
- Gasfitting and plumbing need a licence for the state the work is in, and gas work must be tested before handover.
Questions
Do plumbers need a SWMS?
How deep can a trench be before it needs shoring?
Can I cut old asbestos cement pipe?
Is this plumbing SWMS free to use?
More SWMS templates
- Working at heights
- Electrical
- Carpentry
- Air conditioning
- Solar installation
- Roofing
- Scaffolding
- Concreting
- Excavation
- Demolition
- Painting
- Tiling
- Landscaping
- Builders clean
- Pest control
By state: SWMS template NSW · SWMS template QLD · SWMS template VIC · SWMS template WA · SWMS template SA · Blank SWMS template
Attach the SWMS to every job
Fieldmox runs quotes, scheduling, the technician app and invoicing in one place. Save the SWMS on the job next to the quote and photos, so it's there when the builder asks for it, and add "SWMS read and signed" to the visit checklist your crew ticks off on their phone before they start.
Book a meeting