# Electrical SWMS Template (Free, Australia) | Fieldmox

> Free electrical SWMS for Australian electricians: isolation, test before you touch, ceiling spaces and switchboards. Edit online, download Word or PDF.

Source: https://www.fieldmox.com/templates/swms/electrical

1.  [Home](https://www.fieldmox.com/)
3.  [Templates](https://www.fieldmox.com/templates)
5.  [SWMS template](https://www.fieldmox.com/templates/swms)
7.  Electrical

Free template · Australia · Updated November 2026

# Electrical SWMS template

Work on or near energised electrical installations is high risk construction work, so electricians need a SWMS before they start. This one covers planning, isolation and lock-out, proving dead, ceiling spaces, cabling, switchboard work, and testing and commissioning. Edit the steps for your job, add your details, then download it.

Download Word Save as PDF [Edit it online](https://www.fieldmox.com/templates/swms?trade=electrical#builder)

Free, no sign-up. The download adds a worker sign-on table and principal contractor approval.

## The electrical SWMS

8 job steps, from set-up to pack-down. Every step lists its hazards, risk before and after, and the controls.

Work activity

Installation, alteration and maintenance of low-voltage wiring, switchboards, lighting and power outlets in an existing building, including work in ceiling spaces.

High risk construction work

-   On or near energised electrical installations

PPE

Safety glasses, Steel-cap boots, Work gloves, Insulated gloves (rated), P2 respirator, Knee pads, Arc-rated clothing

Plant and equipment

-   Personal danger locks, tags and lock-out devices
-   Voltage tester and proving unit (CAT III/IV)
-   Insulation resistance and loop impedance tester
-   Insulated hand tools
-   Platform ladder, crawl boards, torch
-   Tested and tagged power tools and leads with RCD

Licences and training

-   General construction induction (White Card)
-   Electrical licence for the state the work is in
-   Low-voltage rescue and CPR (current)
-   Asbestos awareness for work in older buildings

Job steps, hazards, risk ratings and control measures

#

Job step

Hazards

Risk

Control measures

Residual

Responsible

1

Plan the job and check the site

-   Unknown circuits or incorrect drawings
-   Asbestos in older switchboards and ceilings
-   Other trades working nearby

Medium

-   Confirm the scope with the client and find the main and distribution boards
-   Check the asbestos register for buildings built before 1990; don't drill or cut suspect material
-   Agree with the site supervisor when power can be isolated and tell affected people
-   Every worker reads and signs this SWMS before starting

Low

Supervisor

2

Isolate and lock out the circuit

-   Electric shock from the wrong circuit being isolated
-   Someone switching the power back on
-   Back-feed from generators or solar

High

-   Identify the correct isolation point and switch off
-   Fit a personal danger lock and tag to every isolation point; each worker uses their own lock
-   Isolate solar inverters, batteries and generators that could back-feed the circuit
-   Treat every conductor as live until it has been tested dead

Low

Licensed electrician

3

Test before you touch

-   Faulty tester giving a false 'dead' reading
-   Induced or residual voltage

High

-   Prove the tester on a known live source, test all conductors, then prove the tester again
-   Test phase to phase, phase to neutral and phase to earth
-   Discharge capacitors before touching

Low

Licensed electrician

4

Work in ceiling spaces and under floors

-   Heat stress
-   Falling through the ceiling
-   Damaged or live cables
-   Insulation fibres and dust
-   Vermin, spiders and snakes

High

-   Isolate the circuits in the ceiling space before going in where possible
-   Walk on joists or crawl boards, never on the plasterboard
-   Work in the cooler part of the day and limit time in hot roof spaces; take water
-   Wear a P2 respirator, long sleeves and gloves; use a torch, not a lead light
-   Someone outside the space knows you are in there

Medium

All workers

5

Run cables, drill and chase walls

-   Hidden water, gas and electrical services
-   Dust, including silica from masonry
-   Noise
-   Tool injuries

Medium

-   Scan walls and floors with a detector and check plans before drilling
-   Use on-tool dust extraction or wet methods for masonry; wear a P2 respirator
-   Wear hearing protection when using hammer drills and chasers
-   Use tested and tagged tools through an RCD

Low

All workers

6

Terminate and work on switchboards

-   Arc flash
-   Contact with adjacent live parts
-   Falling parts or tools into the board

High

-   Isolate the board where possible; if parts stay live, shroud them and use insulated tools
-   Wear arc-rated clothing and a face shield as the risk assessment requires
-   Use a safety observer trained in low-voltage rescue when working near exposed live parts
-   Keep the board tidy and account for every tool before closing it

Medium

Licensed electrician

7

Test, commission and re-energise

-   Shock during energised testing
-   Faulty installation energised

High

-   Do the required tests (earth continuity, insulation resistance, polarity, correct circuit connection, RCD operation) before energising
-   Use rated test leads and probes
-   Tell everyone before re-energising; remove locks only after the area is clear
-   Give the customer the certificate of compliance the state requires

Low

Licensed electrician

8

Clean up and hand over

-   Off-cuts and dust left for others
-   Covers left off

Low

-   Refit every cover and escutcheon
-   Remove off-cuts and vacuum dust
-   Explain any changes to the client and leave the board labelled

Low

Licensed electrician

## Rules that apply to electrical work

-   Don't work live. The WHS Regulations only allow energised work in narrow cases (such as testing and fault finding), with a risk assessment and a safety observer.
-   Follow AS/NZS 4836 (safe working on or near low-voltage electrical installations) and AS/NZS 3000 (the Wiring Rules).
-   Test before you touch: prove the tester on a known source, test the circuit, then prove the tester again.
-   Portable tools and leads on construction sites are tested and tagged, and protected by an RCD (AS/NZS 3012).
-   In buildings built before 1990, check the asbestos register: older switchboard backing panels and some cable ducts contain asbestos.

## Questions

Do electricians need a SWMS?

Yes, whenever the work is construction work on or near energised electrical installations or services, which covers most electrical work on building sites. It's high risk construction work, so a SWMS is required before work starts. Builders usually ask for it before you're allowed on site.

Can an electrician work live?

Only in limited cases. The WHS Regulations ban live work unless, for example, it's needed for testing or fault finding, or isolating would create a more serious risk. Even then you need a risk assessment, the right equipment and a safety observer. Plan to isolate and lock out.

What standard covers safe electrical work in Australia?

AS/NZS 4836 covers safe working on or near low-voltage electrical installations and equipment. AS/NZS 3000 (the Wiring Rules) covers how the installation is done and tested, and AS/NZS 3012 covers electrical installations on construction and demolition sites.

Is this electrical SWMS free to use?

Yes. Download it as Word or PDF with no sign-up, or open it in the online builder to change the steps and add your business details first. Check it against your own job and site before you use it.

## More SWMS templates

-   [Working at heights](https://www.fieldmox.com/templates/swms/working-at-heights)
-   [Carpentry](https://www.fieldmox.com/templates/swms/carpentry)
-   [Plumbing](https://www.fieldmox.com/templates/swms/plumbing)
-   [Air conditioning](https://www.fieldmox.com/templates/swms/air-conditioning)
-   [Solar installation](https://www.fieldmox.com/templates/swms/solar)
-   [Roofing](https://www.fieldmox.com/templates/swms/roofing)
-   [Scaffolding](https://www.fieldmox.com/templates/swms/scaffolding)
-   [Concreting](https://www.fieldmox.com/templates/swms/concreting)
-   [Excavation](https://www.fieldmox.com/templates/swms/excavation)
-   [Demolition](https://www.fieldmox.com/templates/swms/demolition)
-   [Painting](https://www.fieldmox.com/templates/swms/painting)
-   [Tiling](https://www.fieldmox.com/templates/swms/tiling)
-   [Landscaping](https://www.fieldmox.com/templates/swms/landscaping)
-   [Builders clean](https://www.fieldmox.com/templates/swms/cleaning)
-   [Pest control](https://www.fieldmox.com/templates/swms/pest-control)

By state: [SWMS template NSW](https://www.fieldmox.com/templates/swms/nsw) · [SWMS template QLD](https://www.fieldmox.com/templates/swms/qld) · [SWMS template VIC](https://www.fieldmox.com/templates/swms/vic) · [SWMS template WA](https://www.fieldmox.com/templates/swms/wa) · [SWMS template SA](https://www.fieldmox.com/templates/swms/sa) · [Blank SWMS template](https://www.fieldmox.com/templates/swms)

## Attach the SWMS to every job

Fieldmox runs quotes, scheduling, the technician app and invoicing in one place. Save the SWMS on the job next to the quote and photos, so it's there when the builder asks for it, and add "SWMS read and signed" to the visit checklist your crew ticks off on their phone before they start.

[Book a meeting](https://www.fieldmox.com/book)
